Road Microsurfacing Beginning Wednesday 7/17/19

The final phase of the summer road maintenance program will be taking place beginning on Wednesday July 17, 2019.  This phase will involve a microsurfacing process which will be applied to the following streets in two installments over two consecutive days, weather permitting:

Day 1 and 2:  7/17 and 7/18/19
Barnegat Road
Ogden Road
Dan’s Highway
Valley Road
Parade Hill Lane
Forest Street
Beacon Hill Lane
 
Day 3 and 4:  7/22 and 7/23/19
Transfer Station Access Road
Transfer Station/Sewer Plant
Highway Access Road
Marshall Ridge Road
Sunrise Avenue
Bickford Lane
Skyview Lane

Each application will require up to twenty (20) minutes to set and be ready for traffic so expect minor delays.  Residents on those roads directly affected have received additional information.  Further questions can be directed to the Director of Public Works, Tiger Mann at (203) 594-3056, Tiger.Mann@newcanaanct.gov or Highway Superintendent Mose Saccary at (203) 594-3709, Mose.Saccary@newcanaanct.gov.