Road Construction Updates

For any information regarding pending or proposed construction work, please do not hesitate to contact the Department of Public Works at (203) 594-3054.  We appreciate your patience and cooperation during these investments in our Town’s infrastructure.  For daily information please follow us at #NewCanaanDPW (on Twitter) or @NewCanaanDPW (on Instagram.)  Thank you.

Our Pave, 2024 - Local Roads Project is underway.  The following schedule, weather-dependent, is provided below.  Police Officers or Traffic Personnel will be on-site to assist motorists through or around the work area(s).  We ask motorists to plan ahead for possible delays, etc.


DPW Update 7/9/2024 - The Department of Public Works will be chipsealing the following roads beginning tomorrow, Wednesday, July 10, 2024, weather permitting. The chipseal will remain in place for approximately three (3) weeks. At that time, a Micro-Thin Overlay will placed on top of the roadway. The roadway will then be re-striped where applicable.  Residents are asked to plan additional time and find alternative routes during this road resurfacing project.  For questions, please do not hesitate to contact the Department of Public Works at (203) 594-3054.  We thank you in advance for your help and cooperation.

Wednesday, July 10, 2024                                            Thursday, July 11, 2024

Benedict Hill Rd. Laurel Rd. ( From Turner Hill Rd. to Soundview Ln.)
Evergreen Rd. Ponus Rdg. (From Greenley Rd. to Clearview Ln.)
Valley Rd. (From Ferris Hill to Hickok Rd) Old Norwalk Rd. (From Main Street to Cecil Pl.)




DPW Update 7/9/24 - List of Streets for Resurfacing July 2024

DPW Update 7/7/24 - The Department of Public Works will be re-paving Little Brook Road tomorrow, Monday, July 8, 2024, weather permitting.  Work is estimated to take two (2) days to complete.  Emergency Vehicles, School Buses and Local Traffic (Visitors to East School and Residents of Little Brook Road Only) will be allowed access.  Please find alternate routes and allow additional time due to the detour.  For questions, please do not hesitate to call the DPW at (203) 594-3054.



DPW Update 7/02/24:  
The Department of Public Works will finish striping the Locust Avenue Parking Lot and the Lumberyard Parking Lot on 7/2/24. Therefore both lots will be closed. For Locust Avenue, Patrons are asked to park in the Park Street, Playhouse Lot, or other on-street parking spaces in Town. For the Lumberyard Lot, Patrons are asked to park in the lower level of the lot. The work is estimated to take one (1) day to complete, weather permitting. Please call the DPW at (203) 594-3054 for questions. 


DPW Update 7/01/24:
 
The Department of Public Works will be restriping the Locust Avenue and the Lumberyard Parking Lot today. As a result, both lots will be closed for the day.  The restriping work is expected to take one day to complete, weather permitting.  For any questions, please contact the DPW at (203) 594-3054.

  • Locust Avenue Parking Lot: Patrons are advised to use the Park Street Lot, Playhouse Lot, or other available on-street parking spaces.
  • Lumberyard Parking Lot:      Patrons are advised to park on the lower level of the lot.

 

DPW Update 6/25/24: The Locust Avenue Lot will be open tomorrow morning for patrons.  The Lumberyard Lot was opened this morning.  Thank you for your patience and cooperation.

Crack-sealing:  The Department of Public Works will complete crack-sealing on our local roads tomorrow, June 26, 2024, based on the following schedule, weather permitting. Please pay attention to the Traffic Personnel and allow additional time for your activities. Please call DPW at (203) 594-3054 with any questions.

6/26/24:
- Forest Street
- Country Club Road
- Deep Valley Road
- Valley Road


DPW Update 6/24/2024:
The Department of Public Works will continue to crack-seal our local roads tomorrow, 6/25/2024, based on the following schedule, weather permitting: Please pay attention to the Traffic Personnel and allow additional time for your activities. Please call DPW at (203) 594-3054 with any questions.

6/25/24:
- Marshall Ridge Road
- Willowbrook Lane
- Beacon Hill Lane
- Pastures Lane
- Borglum Road
- Twin Ponds Lane


DPW Update 6/24/2024: The Department of Public Works will be resurfacing the Locust Avenue Parking Lot tomorrow, 6/25/24.  Patrons are asked to park in the Park Street or Playhouse Lot or other on-street parking spaces in Town. The work is estimated to take one (1) day to complete, weather permitting. If you have any questions, please call the DPW at (203) 594-3054.


DPW Update 6/23/2024:
Eversource plans the following work the week of 6/24/24 in our downtown area.  No work is planned for Thursday or Friday.  Please call DPW at (203) 594-3054 with any questions.

Daytime: Monday and Tuesday
Park St at Elm St - 70 Main St

Nighttime: Wednesday
Park St at Elm St
- changeover of services
- for outages - customers have been notified


DPW Update 6/23/2024:
The Department of Public Works will continue to crack-sealing our local roads tomorrow, June 24, 2024, based on the following schedule, weather permitting:

Day #1:
- Hemlock Hill Road
- Dunning Road
- Parade Hill Lane
- Bennington Place
- Bickford Lane
- Marshall Ridge Road

Please pay attention to the Traffic Personnel and allow additional time for your activities. Call DPW at (203) 594-3054 with any questions.



DPW Update 6/23/2024: The Department of Public Works will be resurfacing the upper portion (northern) of the Lumberyard Parking Lot tomorrow, 6/24/24. Patrons are asked to utilize the driveway adjacent to the bank and park in the lower (southern) portion of the parking lot. The work is estimated to take one (1) day to complete, weather permitting. Please call DPW at (203) 594-3054 for questions.



DPW Update 6/17/24:
Road Work Update - Week of 6/17/24: The following work is planned for the week of 6/17/24:
Crack-sealing: - Crack-sealing: All crack-sealing work has been delayed approximately one (1) week. The contractor should resume next week weather permitting.

East Elementary School: - Contractors will continue sidewalk and curbing installation at East School primarily in the traffic circle at the entrance to the school. The traffic circle and Little Brook Road are scheduled to be paved prior to school re-opening in late August. Work is planned to continue throughout the Summer.

West Elementary School: - Contractors will begin sidewalk and curbing installation at West School in the traffic circle at the entrance to the school and throughout the entire parking lot. The traffic circle and parking lot are scheduled to be paved prior to school re-opening in late August. Work is planned to continue throughout the Summer.

Saxe Basketball Court: - Contractors will begin installation of a new basketball court and appurtenances at Saxe School. The court is scheduled to be paved and coated prior to school re-opening in late August. Work is planned to continue throughout the Summer. The court will be closed during the construction period. Thank you,

Locust Avenue and Lumberyard Parking Lots: - Both parking lots are scheduled to be resurfaced the week of 6/24/24 weather permitting. Each lot will be closed during resurfacing and should be open the day after. Work is slated to take 1-2 days per lot. Patrons are asked to make alternative arrangements for parking during this time.

Please contact the DPW at (203) 594-3054 with any questions or concerns.

DPW Update 6/14/2024: #2 CRACK SEALING LOCAL ROADS.  The Department of Public Works will continue to crack-sealing our local roads today, June 14, 2024, based on the following schedule, weather permitting:

- Barnegat Road - Wakeman Road - Ogden Road - Dans Highway - Wellesley Drive - Country Club Road West - Hemlock Hill Road - Dunning Road - Bennington Place - Hanford Lane - Willow Brook Lane - Marshall Ridge Road - Sunrise Avenue

Please pay attention to the Traffic Personnel and allow additional time for your activities.  Please call DPW at (203) 594-3054 with any questions. Thank you.


DPW Update 6/14/2024
:  Harrison Avenue Utility Work. Aquarion Water will be working on lower Harrison Avenue today, Friday, June 14, 2024, to repair a damaged lateral. Emergency Vehicles, School Buses, and Local Traffic will be provided access. Motorists are asked to find alternative routes. Thank you.


DPW Update 6/12/2024: 
The Department of Public Works will be crack-sealing our local roads beginning June 12, 2024, based on the following schedule, weather permitting. Please pay attention to the Traffic Personnel and allow additional time for your activities. Please call DPW at (203) 594-3054 with any questions.

Day #1:    Day#2:   Day#3:   Day#4:
Bald Hill Road   Pequot Lane   Laurel Road   Old Norwalk Road
Journeys End Road   Turtle Back Road East   Valley Road   Willow Brook Lane
Fox Run Road   Turtle Back Road West   Ramhorne Road   Bickford Lane
Benedict Hill Road   Turtle Back Road   Ponus Ridge   SkyView Lane
Evergreen Road       Rilling Ridge   Thurton Drive
Partridge Road           Welles Lane
             
             
Day#5:   Day#6:    Day#7:     
Barnegat Road   Rippowam Road   Bennington Place    
Wakeman Road   Wellesley Drive   Hanford Lane    
Ogden Road   Country Club Road   Willow Brook Lane    
Dans Highway   Hemlock Hill Road   Marshall Ridge Road    
Colonial Road   Dunning Road   Sunrise Avenue    
Deep Valley Road   Partridge Hill Lane   Beacon Hill Lane    
Valley Road   Twin Pond Lane    Pasture's Lane    
        Borglum Road    
        Forest Street    



DPW Update 6/10/2024: Aquarion Water Company will be performing fire flow testing this evening beginning at 6 pm and lasting approximately 2 hours. The following roads in Town will be affected:

Gerrish Ln New Canaan CT 06840
Hampton Ln New Canaan CT 06840
Holmewood Ln New Canaan CT 06840
Oenoke Rdg New Canaan CT 06840
Parade Hill Ln New Canaan CT 06840
Parade Hill Rd New Canaan CT 06840

During and after this scheduled fire flow test, some customers may experience discolored water. You may want to use stored water for drinking and cooking and delay clothes washing until the water is clear. Run your cold water faucet until the water appears clear, prior to resuming use for these purposes.  For questions or concerns, please contact Aquarion directly.

DPW Update 6/09/2024: SIDEWALK INSTALLATION - EAST SCHOOL The Town will replace the existing sidewalks along Little Brook Road at East School the week of 6/10/24.  Work will be primarily on the shoulder of the road from the entrance to the parking lot to the intersection with Clapboard Hill Road.  Please pay attention to the flaggers and allow extra time for travel.  For further information or other questions please call DPW at (203) 594-3054.

DPW Update 6/09/2024:  Eversource’s Schedule for Work Downtown for the Week of 6/10/24
Construction Crew: - No Work Planned

Underground Crew:  Monday - Friday

- Park Street (Near CVS): Daytime: Connecticut Cable
- 70 Main Street (Near Town Hall): Daytime: Eversource Crews

DPW Update 6/3/24:  Aquarion Water Company will be performing fire flow testing this evening beginning at 6 pm and lasting approximately 2 hours. The following roads in Town will be affected: Gerrish Ln New Canaan CT 06840, Hampton Ln New Canaan CT 06840,
Holmewood Ln New Canaan CT 06840, Oenoke Rdg New Canaan CT 06840, Parade Hill Ln New Canaan CT 06840, Parade Hill Rd New Canaan CT 06840.

During and after this scheduled fire flow test, some customers may experience discolored water. You may want to use stored water for drinking and cooking and delay clothes washing until the water is clear. Run your cold water faucet until the water appears clear, prior to resuming use for these purposes.  For questions or concerns, please contact Aquarion directly. Thank you.

DPW update 5/30/24:  The Town will be resurfacing Cedar Lane tomorrow, May 31, 2024, and Saturday June 1, 2024 (weather permitting)

DPW update  week of 5/27/24:
Turtleback Road South (1 day), Betsy's Lane (1 day), and Cedar Lane (2 days)

DPW update 5/24/2024:  There will be no road resurfacing today along Luke's Woods Road. Road resurfacing will restart on Tuesday, May 28, 2024. Please have a safe and enjoyable Holiday

DPW update 5/22/2024: The Town will continue resurfacing of Luke's Woods Road between Rte. 123 and Michigan Road tomorrow, May 23, 2024 (weather permitting.) Our proposed schedule is as follows: (weather permitting) Remaining Week of 5/20/24: Luke's Woods Road (2 days) Week of 5/27/24: Luke's Woods Road (1 day) Turtleback Road South (1 day) Cedar Lane (2 days) Betsy's Lane (1 day) (Potentially week of 6/3/24)

DPW update 5/21/2024: The Town will be resurfacing Luke’s Woods Road tomorrow, May 22, 2024 (weather permitting.) Our proposed schedule is as follows: (weather permitting) Week of 5/20/24: Lost District Drive (Alan's Lane to St. George's) (1 day) Luke's Woods Road (2 days)
Turtleback Road South (1 day) Week of 5/27/24: Cedar Lane (2 days) Betsy's Lane (1 day)

DPW update 5/20/24: Lost District Drive (Alan's Lane to St. George's) (1 day) Luke's Woods Road (2 days) Turtleback Road South (1 day)

Week of 5/27/24: Cedar Lane (2 days) Betsy's Lane (1 day) The process is called Hot-In-Place Asphalt Recycling.

Hot-In-Place Asphalt Recycling is a process whereby the existing asphalt is heated to a high temperature, scarified, milled, combined with an asphalt rejuvenating product and re-applied. Since no material is removed from the job-site and only an asphalt rejuvenator is applied, there is a considerable cost-savings over other traditional methods. The machine used generates a considerable amount of heat in the recycling process and can, on occasion, cause noticeable leaf discoloration; much the same as occurs each fall. This is a temporary condition that results in no permanent damage to the tree.

Should you have any questions regarding this project please do not hesitate to contact Director of Public Works Tiger Mann at (203) 594-3056 Tiger.Mann@newcanaanct.gov or our Highway Superintendent Mose Saccary at (203) 594-3709 mose.saccary@newcanaanct.gov. Please seek alternate routes to avoid delays. There will be flaggers to direct alternating one-way traffic thru the work zone. Emergency Vehicles, School Buses and Local Traffic are allowed thru the Work Zone. Please let us know if you have any special circumstances or considerations during the proposed work. We thank you for your patience and understanding while we work to improve our road network.

DPW update 5/17/24: The Locust Parking Lot will be resurfaced tomorrow, May 18, 2024. Patrons are asked to find alternative places to park for the day. Work should be completed by the afternoon and re-opened to traffic by the evening. Please do not hesitate to contact the Department of Public Works at (203) 594-3056 with questions or concerns.

DPW update 5/16/24: New Canaan: The Town will be resurfacing Lost District Drive tomorrow, May 17, 2024 (weather permitting.) Our proposed schedule is as follows: (weather permitting) Week - 5/13/24: Lost District Drive (Ponus Ridge to St. George's) (2 days)Week of 5/20/24:Luke'sWoods Road (2 days)Turtleback Road South (1 day)Cedar Lane (2 days)Betsy's Lane (1 day)

The upper (Northern) portion of the Lumberyard Parking Lot will be resurfaced tomorrow, May 17, 2024. Patrons are asked to park in the lower portion of the lot (closest to the tracks) during this work. Work should be completed by the afternoon and re-opened to traffic by the evening. Please do not hesitate to contact the Department of Public Works at (203) 594-3054 with questions or concerns.

DPW Update 5/15/24: The Town will be resurfacing Lost District Drive tomorrow, May 16, 2024 (weather permitting.) Our proposed schedule is as follows: (weather permitting)Week of 5/13/24: Lost District Drive (Ponus Ridge to St. George's) (2 days) Week of 5/20/24: Luke's Woods Road (2 days) Turtleback Road South (1 day) Cedar Lane (2 days) Betsy's Lane (1 day)The process is called Hot-In-Place Asphalt Recycling.Hot-In-Place Asphalt Recycling is a process whereby the existing asphalt is heated to a high temperature, scarified, milled, combined with an asphalt rejuvenating product and re-applied. Since no material is removed from the job-site and only an asphalt rejuvenator is applied, there is a considerable cost-savings over other traditional methods. The machine used generates a considerable amount of heat in the recycling process and can, on occasion, cause noticeable leaf discoloration; much the same as occurs each fall. This is a temporary condition that results in no permanent damage to the tree.Should you have any questions regarding this project please do not hesitate to contact Director of Public Works Tiger Mann at (203) 594-3056 Tiger.Mann@newcanaanct.gov or our Highway Superintendent Mose Saccary at (203) 594-3709 mose.saccary@newcanaanct.gov.Please seek alternate routes to avoid delays.We thank you for your patience and understanding while we work to improve our road network.


DPW Update 5/14/24:   
The Town will be resurfacing Lost District Drive tomorrow, May 15, 2024.  The process is called Hot-In-Place Asphalt Recycling. Hot-In-Place Asphalt Recycling is a process whereby the existing asphalt is heated to a high temperature, scarified, milled, combined with an asphalt rejuvenating product, and re-applied. Since no material is removed from the job site and only an asphalt rejuvenator is applied, there is considerable cost-savings over other traditional methods. The machine used generates a considerable amount of heat in the recycling process and can, on occasion, cause noticeable leaf discoloration; much the same as occurs each fall. This is a temporary condition that results in no permanent damage to the tree.  Should you have any questions regarding this project please do not hesitate to contact Director of Public Works Tiger Mann at (203) 594-3056 Tiger.Mann@newcanaanct.gov or our Highway Superintendent Mose Saccary at (203) 594-3709 mose.saccary@newcanaanct.gov.  Please seek alternate routes to avoid delays.  We thank you for your patience and understanding while we work to improve our road network.


DPW Update 4/16/24: 
Milling Toby’s Lane, West Hills Road, and Reeder Lane Wednesday, 4/17/24:  Complete above roads and mill Laurel Road (from Canoe Hill to Turner Hill).  Paving beginning Thursday, 4/18/24, or Friday, 4/19/24 Day 1 Danforth Lane and Lantern Ridge Day 2 Pond View Lane, Laurel Road and Begin Indian Rock Road Day 3 Indian Rock Road Day 4 West Hills Road and Reeder Lane Day 5 Toby’s Lane. All work is weather-dependent.  We will be posting changes on X, Instagram, and the Town's Everbridge System.  Please register for Everbridge to receive these postings.

DPW Update 4/16/24:  Laurel Rd between Canoe Hill Rd and Turner Hill Rd will be closed today, Tuesday, April 16th & tomorrow, Wed. April 17th, during working hours for an emergency replacement of a culvert crossing Laurel Rd. Traffic is detoured onto Valley Rd & Ferris Hill.